ADMISSION EVENTS |
Anderson Hall |
Roof replacement has been contracted. Work to be completed Summer 2013. |
Anderson Hall |
Window replacement has been contracted. Work to be completed Summer 2013 |
Athletic Facilities |
Field turf replacement and track resurfacing at Memorial Stadium and Soccer Field expansion project is in progress. |
Berry Hall |
Shower room upgrades for men's side basement are planned for Summer 2013; additional upgrades will be scheduled as funding allows. |
Campus Wide |
Campus dashboard/building metering project in implementation; currently in process of setting up demand limiting. |
Campus Wide |
Upgrade of access control process to include keying software, rekeying buildings, and a new keying scheme in progress. |
Campus Wide |
Arc Flash Hazard Analysis of all electrical systems has been completed and the program in in implementation. |
Campus Wide |
Water main replacement in design development phase. |
Campus Wide |
Sidewalk replacements and bicycle rack pads installation bids are due March 26. Work to be completed Summer 2013. |
Carhart Science |
Phase III reached substantial completion on April 23; punch list items are being addressed. |
Carlson Natatorium |
Pool locker room upgrades to carpet, benches and fixtures are in progress; other upgrades are in planning stages as funding allows. Locker replacement has been contracted.. |
Carlson Natatorium |
Tile repair and regrouting of the swimming pool has been contracted. Work to be completed Summer 2013. |
Connell |
Primary pad mount switch installation that will also service U.S Conn Library; due for completion Summer 2013. |
Morey Hall |
Re-roofing of the flat roof over the lounge area has been contracted. Work to be completed Summer 2013. |
Peterson Fine Arts |
Window and vestibule replacement has been contracted. Installation to be done Summer 2013. |
Recreation Center |
Chilled water system for air conditioning is in process. Work expected to take all Spring and Summer 2013 to complete. |
Rice Auditorium |
Mid-Hall Locker Room upgrades in design with Leo A. Daly architects. |
Student Center |
Replacement carpet planned for upper level south meeting rooms; due for installation Summer 2013. |
Tennis Courts |
Installation of basketball hoops on one of the courts has been completed.. |
U.S. Conn Library |
Program Statement with Jackson-Jackson Associates and Olsson Associates has been completed and approved by the Coordinating Commission. |
Willow Bowl |
Restoration project is in progress with final grading and sod installation remaining. |